Court rules in favor of Metro in pair of state lawsuits brought by Beverly Hills over subway extension


By Steve Hymon, April 2, 2014

A Superior Court judge ruled in favor of Metro on Wednesday in state lawsuits brought by the Beverly Hills Unified School District and the city of Beverly Hills alleging that the environmental studies for the Purple Line Extension project were flawed and needed to be redone.
To put it in plain English: the judge upheld the studies and denied the requests that they be redone, a task which could have potentially cost Metro millions of dollars and delayed construction of the project.

Metro issued this statement about the ruling:

“Metro is pleased that our in-depth, multi-year environmental review process was found valid by the Superior Court.  We look forward to working with all the communities along the alignment, including Beverly Hills, to fulfill our commitment to deliver this regionally significant and beneficial project for the taxpayers of L.A. County.”

The dispute involves Metro’s plans to tunnel under the Beverly Hills High School campus in order to reach the approved Century City station at the intersection of Avenue of the Stars and Constellation Avenue. The station location was selected by Metro for three reasons: to locate a station closer to the heart of Century City, generate higher ridership for the new line and to avoid an active earthquake fault  zone that runalong Santa Monica Boulevard as determined by seismic and geotechnical studies by Metro and its contractors.

The Constellation route meant that the subway would have to tunnel under part of the Beverly Hills High School campus. School District and city officials complained that could damage the school and/or prevent them from building an underground parking garage, among other issues. After a final Metro Board hearing on the matter in May 2012, Metro determined that it was safe to tunnel beneath the campus, the tunnels would not prohibit any new development, noise and vibration levels would be within federal limits, old oil wells in the area do not present an unmitigable risk to tunneling and the project would not prevent the campus from being used as an emergency evacuation center.

Both the city of Beverly Hills and the Beverly Hills Unified School District have also filed lawsuits against the Federal Transit Administration, alleging violations of the National Environmental Policuy Act. The FTA is helping fund the Purple Line Extension and approved the environmental studies for it. Those lawsuits are still in court.

Local funding for the 8.5-mile Purple Line Extension was approved as part of the Measure R half-cent sales tax increase that was supported by 68 percent of Los Angeles County voters in 2008. The project is being built in three phases: phase one is from Wilshire & Western to Wilshire & La Cienega, phase two extends the project to Century City and the third phase extends tracks to two stations in Westwood — one at Wislhire and Westwood and the final one near the Westwood/VA Hospital, just west of the 405 freeway.

Advanced utility relocation for the first phase of the project is underway and the FTA is expected to soon announce a funding agreement for that part of the project. The Metro Board of Directors is scheduled to select a contractor to build the project this summer with construction starting in late 2014. The first phase is currently forecast to open in 2023.